Chestnut Hill Road Construction

Project Description

The Town of Trumbull Engineering Department is currently working on a Roadway Reconstruction of Chestnut Hill Road.

Work will continue until the end of 2019 (weather permitting). Various sections of the road will be closed to through traffic at different times throughout this process. The Town of Trumbull will endeavor to keep disturbance to a minimum.  However, your patience will be much appreciated.  Construction work is anticipated to start at 7:00 AM daily.  All bus stops will remain at their current locations.

Road Work Sign (JPG)

Project Progress

The Town will post updates to this website and include the anticipated two week look ahead for the project. Dates and locations are subject to change if unforeseen factors arise. Vaz Quality Works LLC is the contractor working for the Town on the Chestnut Hill Road Reconstruction project.

5/11/20: 2 Week Look Ahead

Week of May 11th, 2020:

  • Paving Top Course of roadway
  • Paving and repairs to driveway aprons
  • Installation of topsoil behind curbs and landscaping

Week of May 18th, 2020:

  • Paving and repairs to driveway aprons to continue
  • Installation of topsoil behind curbs and landscaping to continue

1/10/20: 2 Week Look Ahead


Winter Shutdown is in effect until further notice

1/03/20: 2 Week Look Ahead

Week of January 6th, 2020:

  • Installation of topsoil behind new curbing
  • Repairing stone retaining walls to continue
  • Lowering of catch basin and manhole structures
  • Adjusting pavement transitions for side roads

Week of January 13th, 2020:

  • Installation of topsoil behind new curbing
  • Repairing stone retaining walls to continue
  • Lowering of catch basin and manhole structures
  • Adjusting pavement transitions for side roads

12/20/19: 2 Week Look Ahead

Week of December 23rd , 2019:

  • Installation of topsoil behind new curbing
  • Repairing stone retaining walls to continue
  • Lowering of catch basin and manhole structures
  • Adjusting pavement transitions for side roads

Week of December 30th, 2019:

  • Installation of topsoil behind new curbing
  • Repairing stone retaining walls to continue
  • Lowering of catch basin and manhole structures
  • Adjusting pavement transitions for side roads

12/13/19: 2 Week Look Ahead

Week of December 16th , 2019:

  • Installation of topsoil behind new curbing to be installed
  • Continue repairing stone retaining walls
  • Paving and repairs of driveway aprons to continue

Week of December 23rd , 2019:

  • Installation of topsoil behind new curbing to be installed
  • Repairing stone retaining walls to continue
  • Paving and repairs of driveway aprons to continue

12/06/19: 2 Week Look Ahead

Week of December 9th , 2019:

  • Installation of topsoil behind new curbing to be installed
  • Begin repairing stone retaining walls
  • Paving and repairs of driveway aprons to begin

Week of December 16th , 2019:

  • Installation of topsoil behind new curbing to be installed
  • Repairing stone retaining walls to continue
  • Paving and repairs of driveway aprons to continue

11/27/19: 2 Week Look Ahead

Week of December 2nd , 2019

  • Paving to continue
  • Landscaping to begin

Week of December 9th , 2019

  • Paving to continue
  • Landscaping to continue
  • Paving and repair of driveway aprons

11/22/19: 2 Week Look Ahead for Chestnut Hill Road Reconstruction Project

Week of November 25th, 2019 

  • Paving of binder to continue

Week of December 2nd , 2019

  • Paving to continue
  • Landscaping to begin

11/15/19: 2 Week Look Ahead for Chestnut Hill Road Reconstruction Project

Week of November 18th, 2019 

  • Reclaiming to begin
  • Paving of binder to continue

Week of November 25th , 2019

  • Paving to continue
  • Landscaping to begin

11/01/19: 2 Week Look Ahead for Chestnut Hill Road Reconstruction Project

Week of November 4th, 2019 

  • Full Depth reconstruction to continue from Francis Street towards Samuel Street
  • Gas line reconfiguration to continue
  • Installation of process

Week of November 11th , 2019

  • Reclaiming of road to begin
  • Paving of binder course

10/25/19: 2 Week Look Ahead for Chestnut Hill Road Reconstruction Project

Week of October 28th, 2019 

  • Full Depth reconstruction to continue from Francis Street towards Samuel Street
  • Prepping of areas including gas line reconfiguration
  • Installation of process

Week of November 4th , 2019

  • Full Depth reconstruction to continue
  • Prepping of areas for full depth reconstruction to continue

10/17/19: Update on Chestnut Hill Road Paving Project

Unfortunately, the Contractor hired to repave Chestnut Hill Road has fallen behind schedule. 

The Town has been pressing the Contractor to complete the job and is prepared to pursue all remedies. 

Town personnel have been monitoring the project closely and expect that the Contractor will achieve substantial completion of the project before the asphalt plants shut down for the winter. 

We ask for your patience.

10/04/2019: 2 Week Look Ahead for Chestnut Hill Road Reconstruction Project

Week of October 7th, 2019

  1. Reclaiming of road to begin
  2. Grading and paving to begin

Week of October 14th, 2019

  1. Reclaiming of road to continue
  2. Grading and paving to continue

9/27/2019: 2 Week Look Ahead for Chestnut Hill Road Reconstruction Project

Week of September 30th, 2019

  1. Road elevations and alignment alterations to continue
  2. Installation and relocation of utilities to continue

Week of October 7th, 2019

  1. Reclaiming of road to begin