Upper Long Hill School House Restoration Project

Get Involved

We are excited to complete the restoration of the historic Upper Long Hill Schoolhouse.  In order for the community to reach that goal, there is a need to gain funding and donations toward this wonderful project.  The goal is of $100,000. This funding will come through corporate sponsorships, grants, and personal donations. 

If you would like to make a donation to this project, please follow this link to make your contribution.

If you would like to get more involved, please contact Rina Bakalar, Director of Economic & Community Development at rbakalar@trumbull-ct.gov or John Naeher of Christian Heritage School at jnaeher@chskingsmen.org.

About the Project

Trumbull has been presented with a rare opportunity to honor its heritage and bring a powerful symbol of town pride into the present. During recent renovations at Long Hill Green, a small structure slated for demolition caught the attention of the community. At first glance, it seemed insignificant. However, a mandated demolition review by the Trumbull Demolition Review Committee, a team led by Zoning Enforcement Officer Brian Fitzgerald, Historical Society Co-President Debra Silber, and Historical Society member and Christian Heritage School Student Life Coordinator John Naeher revealed something remarkable: this was no ordinary building. Constructed in 1894, it was the last one0room schoolhouse built in Trumbull, the Upper Long Hill School.

This modest building carries deep historical and emotional significant. It marked the beginning of Miss Jane Ryan’s distinguished career in education, a figure who would go on to found Trumbull’s first public library. Among the school’s students were the children of Igor Sikorsky, the famed helicopter pioneer, further anchoring the schoolhouse to Trumbull’s legacy. 

Once its true history was uncovered, a team came together to safeguard the schoolhouse’s remains, and the Parks Superintendent Dmitri Paris worked with the committee, private developer, and volunteer experts to dismantle and relocate the structure. The leadership of those who recognized its historical significance was instrumental in ensuring the original components were saved. Once relocated, an initiative led by John Naeher engaged student and families from Christian Heritage School to volunteer their time clearing and preparing the recovered boards for future reconstruction. These materials will remain safely stored at the school until the fundraising goal is met. 

Click here for project photos and more historic background (PDF).

Rebuilding the Historic Schoolhouse: A Call to Action

The vision is to reconstruct the schoolhouse on Town Hall property and transform it into vibrant, multipurpose community space. More than just a building, it will serve as a bridge between Trumbull’s past and future – a place to reflect on where we’ve been, who we are, and what we an accomplish together.

To bring this vision to life, community involvement is essential. Volunteers are needed to contribute time, skills, materials, and financial support. Whether you’re a tradesperson, a local business, or simply someone eager to help, your participation will make a lasting impact. See below for specific roles that need to be filled.

The fundraising goal is $100,000, and with enough support and enthusiasm, the reconstructed schoolhouse could open as early as fall 2026. Let’s come together to celebrate our shared history and build something meaningful for future generations!

Specific Needs

Contractors
We are in need of skilled professionals for roofing, siding, and general construction to assist with reconstruction efforts. Components include framing, painting, windows, roofing, interior, walls/trim, flooring, slab/power, blending corners/walls/siding, cupola/bell, entrance overhand, landscaping, lighting, HVAC, stove stack, insulation, signage/plaque/historic information, etc.

Materials
We are seeking building materials, including plywood, shingles, insulation, etc.

Volunteers
Volunteers are needed to assist with debris removal, distribution of supplies, cleanup, etc.

Project Timeline

  • Spring 2025:  Disassembly and storage of structure
  • Spring 2025 – On going Fundraising
  • Summer – Fall 2025: Project design
  • Fall 2026: Permits, Utilities, Slab
  • Spring - Summer 2027: Framing, Roofing, Windows, Trim, Paint, Interior
  • Summer 2027: Completion Goal