Posted on: June 3, 2013

[ARCHIVED] 4 week Look-Ahead for Paving at Contract IV Area Roads

6/3/13 – 4 week Look-Ahead for Paving at Contract IV Area Roads

At this time, below is the anticipated 4 week look ahead for construction activity in the North Nichols Area. Dates and locations are subject to change based on numerous unforeseen factors, however, the Town of Trumbull shall provide an update on a weekly basis. These updates shall be posted on our website.

Various sections of the roads will be closed at different times throughout this process. The Town of Trumbull Road will endeavor to keep disturbance to a minimum. However, your patience will be much appreciated. Construction work is anticipated to start at 7:00 am daily.

Week of June 3rd, 2013:

Drainage construction will continue on the following roads: Columbine Road, Saybrook Road, Partridge Lane, Jerusalem Hill, Hilltop Circle


Week of June 10th, 2013:

Drainage construction will continue on the following roads: Jerusalem Hill, Hilltop Circle, Rennison Road, Old Green,

Roadway Excavation will begin in the Columbine Road Area: Columbine Road, Tamarack Circle, Heartwood Lane, Kenwood Lane, Ethel Road, Oriole Circle, Rennison Road.

Week of June 17th, 2013:

Drainage construction will continue on the following roads: Old Green Road, MacDonald Road, Hillandale Terrace, Skyview Drive, Pachaug Road

Roadway Excavation/Paving will continue in the Columbine Road Area: Columbine Road, Tamarack Circle, Heartwood Lane, Kenwood Lane, Ethel Road, Oriole Circle, Rennison Road.

Week of June 24th, 2013:

Drainage construction will continue on the following roads: Old Green Road, MacDonald Road, Hillandale Terrace, Skyview Drive, Pachaug Road

Roadway Excavation/Repaving will continue in the Columbine Road Area: Columbine Road, Tamarack Circle, Heartwood Lane, Kenwood Lane, Ethel Road, Oriole Circle, Rennison Road. 