News Flash Home
The original item was published from 10/31/2013 12:00:00 AM to 10/28/2019 4:44:39 PM.

News Flash

Town News

Posted on: October 31, 2013

[ARCHIVED] 11/6/13 – 3 week Look-Ahead for Paving at Contract IV Area Roads

11/6/13 – 3 week Look-Ahead for Paving at Contract IV Area Roads

At this time, below is the anticipated 4 week look ahead for construction activity in the North Nichols Area. Dates and locations are subject to change based on numerous unforeseen factors, however, the Town of Trumbull shall provide an update on a weekly basis. These updates shall be posted on our website.

Various sections of the roads will be closed at different times throughout this process. The Town of Trumbull Road will endeavor to keep disturbance to a minimum. However, your patience will be much appreciated. Construction work is anticipated to start at 7:00 am daily.

Please note, all school bus stops will remain in their current designated locations.

Week of November 4th, 2013

Roadway Topsoil work will continue on: Erwin Street and North Street.

Drainage installation will continue on Primrose Drive, North Stowe Place, Copper Kettle Road, Kingsbury Drive and Red Fox Lane.

Week of November 11th, 2013 – Week of November 18th, 2013

Roadway milling and paving will continue on Red Fox Lane, Copper Kettle Road and North Field Drive (from Kingsbury Road to Copper Kettle Road).

Drainage installation will continue on North Stowe Place, Copper Kettle Road and Kingsbury Drive.

Facebook Twitter Email