As of July 13th, 2020, the temporary traffic signal will be in place and operating at the Strobel Road culvert located between Doe Hollow Drive and Hemlock Trail. Alternating one way traffic will be used for the duration of the culvert repairs, which is anticipated to be complete the 1st week of September, 2020.
On July 31st and August 3rd, the phase 2 detour from Gray Rock Road to Chatham Drive will be used between the hours of 7:00am and 5:00pm:
Detour Map
Details on the location and type of work will be continuously updated and posted to the Town of Trumbull’s website.
Week of August 3rd, 2020:
- Establish new traffic pattern for the North lane at the Stobel Culvert in preparation to switch alternating traffic lanes
- Install remaining box culvert units on south side of culvert
- Install poured concrete footings and cutoff walls on south side of culvert
Week of August 10th, 2020:
- Begin construction of culvert parapet and wing walls on the south side of roadway