Below is the anticipated 2 week look ahead for Strobel Road Reconstruction Project.    Dates and locations are subject to change based on numerous unforeseen factors.  The updates shall be posted on this website.  Colonna Concrete & Asphalt Paving LLC is the contractor working for the Town.

This is a long-term project that will require multiple years to complete (weather dependent). Location of work along Strobel Road will be updated as the project progresses. Various sections of the road will be closed to “Thru Traffic” at different times throughout this process.  The Town of Trumbull will endeavor to keep disturbance to a minimum.  However, your patience will be much appreciated.  Construction work is anticipated to start at 7:00 am daily.  All bus stops will remain at their current locations.

Starting on November 18, 2019, the contractor will begin work between Chatham Drive and Daniels Farm Road. This work will be limited to drainage improvements within or close to the roadway shoulder. 2-lane traffic will be maintained at all times. Current Phase 2 detour from Chatham Drive to Gray Rock Road will remain active until further notice.

Week of November 18th , 2019 

  • Continue to furnish and install drainage
  • Continue clearing and grubbing
  • Construction layout and establish grade for road reconstruction
  • Installation of sediment and erosion control devices to continue

Week of November 25th , 2019 

  • Continue to furnish and install drainage
  • Continue clearing and grubbing
  • Construction layout and establish grade for road reconstruction
  • Installation of sediment and erosion control devices to continue